1. The project commenced on September 5th, 2016 and will be handed over on January 27th, 2019. On behalf of the contractor, a detailed program of works was submitted. Miss Kaoli needed to familiarize herself with the design, construction, contract terms and all other aspects of the project.
2. The objective was to manage the information and prepare the time schedule in collaboration with the construction engineering team, with a submission deadline of November 11th, 2016.
3. Regular reporting and management of actions and events was required.
4. Relationships were to be handled in a professional manner.
5. Reporting was to the Project Manager of the project and the Marine Works Manager.