1. Document some defects prior to the taking over and prepare a snagging list and then inspect the remedies
2. Assure that the Technical Specifications included in the agreement have been implemented and all necessary certificates / information will be handed to the Stakeholder
3. Visual inspection took place at ‘RIA COURT 61‘on 21st of February 2020 for a preliminary Taking Over based on contract specification and finalized on the 26th of February 2020.